Construction on Mars, Part 2, Appendix: Height

I had said in an earlier post that I would try to post once a week. That was wildly optimistic and life intervened. Instead of posting once a week, I will try to post on an ongoing basis.

One thing I mentioned in the previous post was that that the height of structures designed according to the design I described really would tend to be larger than their breadth. I will show the math behind that in this post.

In order to do so, I will start off with a very simplistic model for the cost of the structure:

Eq1

Where C is the total cost of construction, CW is the cost of the counterweight structure, CS is the cost of the compressive structure, CJ is the cost of the outer pressure jacket, CT is the cost of the tension cables, and CA is the additional cost of other things. I will assume that the structure has a square base with side length x and height z. By assuming simple linear behavior, we can expand each of these terms as follows:

expansions

The constants W, S, J’, J, T, and A are constants of proportionality describing the cost per unit of counterweight, compressive structure, pressure jacket, tension cables, and additional costs respectively. All assume a constant internal pressure driven by physiological needs.

Given a constant internal pressure, the thickness of counterweight is constant, and the amount of counterweight increases with area, x2.

The compressive structure needs to support the full weight of the counterweight, and thus its cross-section is therefore proportional to its total weight, itself proportional to area. Per the first rule of space construction, this force strictly dominates the weight of the compressive structure. The compressive structure also needs to be as tall as the structure, and thus costs an amount proportional to its height, thus total cost is proportional to internal volume, x2z.

The pressure jacket refers to the curved metal structures and framing support members that contain pressure on the outer wall. Cost can be described as being proportional to the external area of the vertical walls of the structure, perimeter times height, 4xz. By introducing a constant J 4 times larger than the initial constant J’, we can simplify the expression to xz.

The tension cables have to bear a load in proportion to the total external area, which means their cross section is proportional to xz, and have length proportional to the width of the building x, so that the cost is proportional to x2z.

The additional cost term is a placeholder and is assumed to be proportional to the internal volume of the structure.

Plugging in the expansion of each term and dividing by the volume, x2z, we can determine the cost per volume of the structure as follows:

cdivv

Naturally we want this C/v value to be as low as possible. We can determine by intuition that the optimum lies somewhere in the middle, rather than at an extreme, and therefore we can determine the answer through differentiation. The optimum is the place where the price per volume remains the same as you modify the aspect ratio of the structure while holding the internal volume constant.

pd

Each of these will, when evaluated and solved, provide the same correct answer:

finaleqfull

Where W is the cost per square meter of the counterweight and J is the cost per four square meters of tensile jacket, and J’ is the cost per single square meter of tensile jacket.

It’s worth mentioning “cost” is, both in general and in this specific case, a pretty complicated thing to talk about. Construction costs can vary widely for similar projects, even within the same country, depending on all sorts of technical and social factors.

As an example, thinking in the abstract: What is the cost of one unit of iron ore, energy, capital (in the form of machines), and labor on Earth? And how will circumstances on Mars change the relative costs of those inputs (and other important inputs) as compared to Earth?

Even comparing between countries on Earth can be complicated. This report on the relative sizes of the economies of the United States and the Soviet Union in the latter half of the Cold War shows how complicated the comparisons can get, even in two developed countries of similar size, at the same time, with similar resource availability.

All this is to say that it would be inappropriate to try to quantify the optimal ratio of height to width. Instead, I will simply make general observations and look at Earth’s costs for reference.

I will speak at greater length on the construction of each element in a later post. Schematically, the tensile jacket is made from stacked layers of steel half-pipe, attached to a frame with sealant to contain internal air. Assuming a typical strength of plain carbon steel of 300 MPa, a safety factor of 5, and each layer being 3 m tall, this will require just 50 kg of steel per square meter or 200 kg per four square meters (more material of some kind will likely be required to reduce the potential for puncture).

The counterweight is made from some bulk material (concrete, or sand, or gravel) contained within a large frame. A 50 kPa internal pressure with a 5% counterweight overload requires 14 tonnes of material per square meter of counterweight.

It does not require much imagination or analysis to believe that 200 kg of formed steel and structure costs less than 14 tonnes of concrete and structure. It is this basic truth, that W > J, that drives the buildings towards more height and less breadth.

This post is part of a series.  You can read the next post here.

5 thoughts on “Construction on Mars, Part 2, Appendix: Height

  1. Torkil Bladt says:

    Very interesting blog, I got the link from Kim Stanley Robinsons facebook page.
    I have also made some thoughts of the problem. I understand your calculations, but I think that you have forgotten some details.
    You claim that the cost/weight of the internal compression structure (columns) will be proportional to the height of the structure. I think that you have forgotten the Euler column formula, where the height is squared. It is much cheaper to carry 10 ton at 10m in tension (a steel wire) than in compression (steel column).
    I have not made any calculations myself, but by intuition I would say that a pressurized membrane (bubble) with a balanced layer of regolit (gravel) on top would be the cheapest. In that way there would only be small membrane forces, so the risk of a large decompression would be minimal.
    Regards Torkil, Denmark

    • Hey Torkil,

      You make a really good point here that I had neglected to consider in this post. I will think about how to address the true limitations in compressive structures associated with Euler bucking and try to post an improved version of this post at a later date.

      Cheers!

      Josh

      • Torkil Bladt says:

        I am trying to figure out what shape an inflated dome should have, if it should be covered with a balanced layer of regolith to reduce radiation and membrane stresses. When doing that I’ll have to take into consideration how steep the slopes of the regolith heap may be. For simplicity I am looking at a tunnel shape rather than a dome shape. I think I can set up the equations for a simple finite element model of beams in a spread sheet, but I am not sure I can set up an optimization calculation.

Leave a comment